The same house costs $31,827 more to permit in Osceola County than in Lake County
Government fees to build one identical 2,000 sq ft single-family home across
10 Florida counties. Impact fees, water and sewer connection charges, and building
permits — every figure transcribed from official county sources with its effective date.
Spread across these counties2.77×for the same house on the same kind of lot. Impact fees drive
52–91% of every stack.
Lake CountyWater and sewer: None — Lake County operates no water or sewer utility
$17,998
$15,328 –$18,426
The most commonly missed number
In Osceola County, water and sewer is charged by Toho Water Authority — a separate independent
special district with its own board and its own $9,943 system development charge. That is 20% of the
total stack, and it appears on no Osceola County fee page. Getting the right utility district is the
difference between a usable estimate and a $10,000 error.
Every figure is transcribed from an official county or Florida Statutes document with
its effective date and a direct link. Gaps are reported as gaps, never estimated.